The California Department of Transportation (Caltrans) plans to implement the closures listed below during the week of June 8-13, 2014, as part of the I-5 Empire Project in Burbank. Closures are subject to change.
Project Information: Information about the project is here.
Major construction operations for June 8-13: Paving the I-5 median between Burbank Boulevard and Cohasset Street; demolition of San Fernando and Victory Place undercrossings.
What to Expect: Residents may hear some construction noise, but it will not exceed levels permitted by state, federal and local regulations.
Closure Information: Closure information for this and other freeway projects is also available on the Caltrans website and the I-5 website.
Real-Time traffic Information: Visit quickmap.dot.ca.gov, go511.com, or call 5-1-1.
NORTHBOUND I-5 CLOSURES
Lanes
- Up to three lanes between Olive Ave. and Hollywood Way: 9 p.m. to 6 a.m.
Note: The most restrictive closures (i.e., the most lanes closed) will occur between midnight and 4 a.m.
Ramps
- Buena Vista Street on-ramp and off-ramp: 9 p.m. to 6 a.m.
SOUTHBOUND I-5 CLOSURES
Lanes
- Up to three lanes between Hollywood Way and Olive Ave.: 9 p.m. to 6 a.m.
Note: The most restrictive closures (i.e., the most lanes closed) will occur between midnight and 4 a.m.
Ramps
- Westbound and eastbound Burbank Boulevard on-ramps: 9 p.m. to 6 a.m.