The California Department of Transportation
(Caltrans) will close the following lanes, ramps, and connectors of the
Golden State Freeway (I-5) and the Ventura Freeway (SR-134) as part of a
$57.8 million improvement project to construct High Occupancy Vehicle (HOV
or carpool) lanes in each direction along I-5 between SR-134 and Magnolia
Boulevard. Closures are subject to change. Detours will be signed.
Golden State Freeway (I-5) Closures
Thursday July 5 through Tuesday July 10, 2012
▪ Northbound I-5 Connector to Eastbound SR-134
TIME: 11 p.m. to 6 a.m. (Until 7a.m. on Saturday July 7th and 9
a.m. on Sunday July 8th)
▪ Southbound I-5 Connector to Eastbound SR-134
TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday July 7th and 9
a.m. on Sunday July 8th)
▪ Westbound SR-134 Connector to Northbound I-5
TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday July 7th and
Sunday July 8th)
▪ Westbound SR-134 Northbound and Southbound San Fernando Road On
Ramp
TIME: 9 p.m. to 6 a.m. (Until 8 a.m. on Saturday July 7th and 9
a.m. on Sunday July 8th)
▪ Northbound I-5 Western Avenue Eastbound and Westbound On Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7th and
Sunday July 8th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Western Avenue Eastbound and Westbound Off Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7th and
Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Western Avenue Eastbound and Westbound On-Ramps
TIME: 7 p.m. to 6 a.m. (Until 9 a.m. on Saturday July 7th and 12
p.m. on Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Western Avenue Westbound and Eastbound Off-Ramps
TIME 7 p.m. to 6 a.m. (Until 10 a.m. on Saturday July 7th and 12
p.m. on Sunday July 8th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo
Avenue Off Ramp
TIME: 9p.m. to 6 a.m. (Until 9 a.m. on Saturday July 7th and 10
a.m. on Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo
Avenue Off Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7th and
Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo
Avenue On Ramp
TIME: 9 p.m. to 6 a.m. (Until 10 a.m. on Saturday July 7th and 11
p.m. on Sunday July 8th)
▪ Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo
Avenue On Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7th and
Sunday July 8th)
▪ Northbound I-5 Eastbound and Westbound Alameda Avenue Off and On
Ramp
Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7thand
Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Eastbound and Westbound Alameda Avenue Off and On
Ramp
Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday July 7th and
Sunday July 8th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Eastbound and Westbound Burbank Boulevard On Ramp
Time: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday July 7th and 10
a.m. on Sunday July 8th)
· Northbound I-5 Westbound Colorado Boulevard On Ramp
Time: 10 p.m. to 7 a.m. (Until 9 a.m. on Sunday July 8th)
▪ Northbound I-5 from Colorado Boulevard to SR-134
TIME: Up to three lanes – 10 p.m. to 6 a.m.(Until 10 a.m. on
Saturday July 7th and 9 a.m. on Sunday July 8th)
Four lanes- 1 a.m. to 5 a.m.
▪ Northbound I-5 from SR-134 to Burbank Boulevard
TIME: Up to two lanes – 10 p.m. to 7 a.m. (Until 8 a.m. on Sunday
July 8th)
Three lanes- 1 a.m. to 5 a.m.
▪ Southbound I-5 from Burbank Boulevard to SR-134
TIME: Up to two lanes – 10 p.m. to 6 a.m. (Until 9 a.m. on Sunday
July 8th)
Three lanes –1 a.m. to 5 a.m.
About the Project
This project is building a high occupancy vehicle (HOV) lane in each
direction along the Golden State Freeway (I-5) between the Ventura Freeway
(SR-134) and Magnolia Boulevard in Burbank, a total distance of 5.4 miles
(2.7 miles in each direction). It is also constructing sound walls and
retaining walls.