New Caltrans Advisory for I-5 Project

0
566

CONSTRUCTION ACTIVITIES

  • On October 4, 2015, from 2 a.m. to 6 a.m., I-5 will be fully closed from Hollywood Way to Burbank Boulevard so that Burbank Water and Power can safely relocate overhead power lines. The on- and off-ramps between Hollywood Way and Burbank Boulevard will be closed. Southbound I-5 motorists will be diverted at Hollywood Way and northbound I-5 motorists will be diverted at Burbank Boulevard.  A signed detour will be posted.
  • For the safety of motorists during pile driving for a new railroad bridge, one lane of northbound Buena Vista Street will be closed on weekdays, Monday through Friday, from 7 a.m. to 3 p.m. through October 16, 2015. For more information click here.

134 to Magnolia Boulevard

Bridge Widening Activities: 

+ Construction of concrete barrier rails at Western Avenue and Alameda Avenue

+ Construction of bridge supports underneath the Los Angeles River Bridge

+ Slab construction at Alameda Bridge

+ Stripping and patching of concrete barrier at Los Angeles River Bridge

Magnolia Boulevard to Buena Vista Street

Burbank Western Channel: Backfilling trench operations.

Old San Fernando Tunnel: Concrete crushing.

Empire Bridge: Installation of falsework to support freeway bridge structure.

Victory Place Bridge: Drilling CIDHs (cast in drilled holes) for bridge support structures.

Buena Vista Bridge (Winona Bridge): Installation of falsework on southbound side.

Buena Vista Railroad Bridge: Pile driving and shoring work.

San Fernando Railroad Bridge:  Demolition of main line track on the northbound side.

Railroad Retaining Wall: Installation of precast panels on the railroad retaining wall between Buena Vista Street and Hollywood Way (night work).

Future New Empire Avenue: Excavation work next to Sharky’s.

Southbound I-5 Retaining Walls: Construction of new retaining walls on southbound I-5 between Empire Avenue and Burbank Boulevard.

Utility Work: Underground utility work on Maria Street north of Empire Avenue and San Fernando Boulevard east of Grismer Avenue.

Closures and Detours

SR-134 to Magnolia Boulevard

+ From September 25, 2015, through October 2017, the Los Angeles River Bike Path between Riverside Drive and just south of the SR-134 overcrossing in the city of Glendale will be closed. For more information and the bike path detour, click here.

+ There will be intermittent closures of the northbound Alameda Avenue and Western Avenue on-ramps Monday, October 5, through Friday, October 9, between 7 a.m. and 3:30 p.m.

Magnolia Boulevard to Buena Vista Street

+ On October 4, 2015, from 2 a.m. to 6 a.m., I-5 will be fully closed from Hollywood Way to Burbank Boulevard. The on- and off-ramps between Hollywood Way and Burbank Boulevard will be closed as well. Southbound I-5 motorists will be diverted at Hollywood Way and northbound I-5 motorists will be diverted at Burbank Boulevard.  A signed detour will be posted.

+ Through October 16, 2015, one lane of northbound Buena Vista Street will be closed on weekdays, Monday through Friday, from 7 a.m. to 3 p.m.  For more information, click here.