The California Department of Transportation (Caltrans) will close the following lanes and ramps of the Golden State Freeway (I-5) as part of a $121 million improvement project to construct High Occupancy Vehicle (HOV or carpool) lanes in each direction along I-5 between SR-170 to Buena Vista Street. Closures are subject to change. Detours will be signed.
*Due to the Holiday there will be no closures on December 31, 2012 and January 1, 2013
Golden State Freeway (I-5) Closures
Monday December 30 through Saturday January 5, 2013
▪ Southbound I-5 Roscoe Boulevard Eastbound and Westbound On-RampTIME: 7 p.m. to 6 a.m. (Until 10 a.m. on Saturday January 5th)▪ Northbound I-5 Roscoe Boulevard Eastbound and Westbound Off-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.▪ Northbound I-5 Sunland Boulevard Eastbound and Westbound Off-Ramp TIME: 8 p.m. to 6 a.m.
9 a.m. to 2 p.m.
▪ Northbound I-5 Sunland Boulevard Eastbound and Westbound On-Ramp
TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
▪ Northbound I-5 Penrose Street Eastbound and Westbound Off-Ramp TIME: 8 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m▪ Southbound I-5 Sunland Boulevard Eastbound and Westbound Off RampTIME: 7 p.m. to 6 a.m. (Until10 a.m. on Saturday January 5th)
▪ Southbound I-5 Sunland Boulevard Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 5th)
▪ Northbound I-5 Tuxford Street Eastbound and Westbound Off and On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Lankershim Boulevard Eastbound and Westbound On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.▪ Northbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
Off and On Ramps TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th) 9 a.m. to 3 p.m.
▪ Southbound I-5 Penrose Street Eastbound and Westbound Off-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Penrose Street Northbound and Southbound On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.
▪ Southbound I-5 Lankershim Boulevard Eastbound and Westbound Off RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
▪ Southbound I-5 Lankershim Boulevard Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until12 p.m. on Wednesday January 3rd)
9 a.m. to 3 p.m.
▪ Southbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
Off and On Ramps TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
Off and On Ramps TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
9 a.m. to 3 p.m.
▪ Northbound I-5 Hollywood Way Eastbound and Westbound On and Off RampTIME: 8 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 5th)
▪ Northbound I-5 Buena Vista Street Eastbound and Westbound On RampTIME: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 5th)▪ Southbound I-5 Hollywood Way Eastbound and Westbound Off RampsTIME: 8 p.m. to 6 a.m. (Until 8 a.m. on Saturday January 5th)▪ Southbound I-5 Hollywood Way Eastbound and Westbound On RampsTIME: 8 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 5th)
▪ Northbound I-5 from Buena Vista Street to Sheldon Street/Laurel Canyon BoulevardTIME: One Lane: 8 p.m. to 6 a.m. (Until 8 a.m. on Saturday January 5th) Three Lanes: 12 a.m. to 4 a.m. ▪ Southbound I-5 from Sheldon Street/Laurel Canyon Boulevard to Buena Vista StreetTIME: Up to Two lanes: 8 p.m. To 6 a.m. (Until 8 a.m. on Saturday January 5th) Three lanes: 12 a.m. to 4 a.m.
About the Project
Caltrans is building an HOV lane in each direction of I-5 between SR-170 and north of Buena Vista Street in Burbank.
Golden State Freeway (I-5) Closures
Saturday December 28 through Monday January 7, 2012
*SB I-5 Eastbound and Westbound Alameda Avenue Off-ramp will have a long-term closure that will last approximately 60 days. It is expected to open on the week ending, January 12, 2013.
*Northbound I-5 Eastbound and Westbound Alameda Avenue Off-ramp will have a long-term closure that will last approximately 60 days. It is expected to open on the week ending, February 15, 2013.
▪ Southbound I-5 Eastbound and Westbound Alameda Avenue Off Ramp Time: 8 p.m. to 6 a.m. (Until 12 p.m. on Sunday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th)
▪ Southbound I-5 Eastbound and Westbound Alameda Avenue On Ramp Time: 8 p.m. to 5 a.m. (Until 12 p.m. on Saturday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th)
▪ Northbound I-5 Eastbound and Westbound Alameda Avenue Off Ramp Time: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday December 29th, 10 a.m. on Sunday December 30th, 9 a.m. on Saturday January 5th and 10 a.m. on Sunday January 6th) 9 a.m. to 3 p.m.
▪ Northbound I-5 Eastbound and Westbound Alameda Avenue On Ramp Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th) 9 a.m. to 3 p.m.
▪ Southbound I-5 Western Avenue Westbound and Eastbound Off-Ramps TIME 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th and Sunday December 30th and 10 a.m. Saturday January 5th and Sunday January 6th)
9 a.m. to 3 p.m. ▪ Southbound I-5 Western Avenue Westbound and Eastbound On Ramps TIME 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th and Sunday December 30th, 10 a.m. on Saturday January 5th and 12 p.m. on Saturday January 6th)
9 a.m. to 3 p.m. ▪ Northbound I-5 Westbound Colorado Boulevard On Ramp Time: 10 p.m. to 6 a.m. (Until 7 a.m. on Saturday January 5th and Sunday January 6th)▪ Southbound I-5 Connector to Eastbound SR-134 TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday January 5th and 9 a.m. on Sunday January 6th)▪ Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue On-RampsTIME: 9 p.m. to 6 a.m. (Until 10 a.m. on Saturday December 29th, 11 a.m. on Sunday December 30th, 10 a.m. on Saturday January 5th and 11 a.m. on Sunday January 6th)
▪ Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue Off RampsTIME: 9 p.m. to 6 a.m. (Until 10 a.m. on Saturday December 29th and 12 p.m. on Sunday December 30th, Saturday January 5th and Sunday January 6th)
9 a.m. to 3 p.m.▪ Northbound I-5 from SR-134 to Burbank BoulevardTIME: Up to two lanes – 10 p.m. to 6 a.m.
Four lanes: 1 a.m. to 4 a.m.
Northbound I-5 from Colorado Boulevard to SR-134TIME: Up to three lanes – 10 p.m. to 6 a.m.
Four lanes: 1 a.m. to 4 a.m.
▪ Northbound I-5 Connector to Westbound SR-134 TIME: 12 a.m. to 6 a.m. ▪ Northbound I-5 Western Avenue Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th)
9 a.m. to 3 p.m. ▪ Northbound I-5 Western Avenue Eastbound and Westbound Off RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th)
9 a.m. to 3 p.m.▪ Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue Off-RampsTIME: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday December 29th, 10 a.m. on Sunday December 30th, 9 a.m. on Saturday January 5th and 10 a.m. on Sunday January 6th)
9 a.m. to 3 p.m.▪ Westbound SR-134 Connector to Northbound I-5 TIME: 11 p.m. to 6 a.m.
▪ Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue On-RampsTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday December 29th, Sunday December 30th, Saturday January 5th and Sunday January 6th)
▪ Southbound I-5 Westbound and Eastbound Burbank Boulevard On RampTime: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday December 29th, 10 a.m. on Sunday December 30th, 9 a.m. on Saturday January 5th and 10 a.m. on Sunday January 6th)
▪ Westbound SR-134 at I-5 intersectionTime: Up to two lanes 8 p.m. to 9 a.m.
Three lanes: 12 a.m. to 7 a.m. ▪ Southbound I-5 from Western Avenue to SR-134TIME: Up to two lanes: 1 a.m. to 4 a.m.▪ Southbound I-5 from Burbank Boulevard to SR-134TIME: Up to two lanes – 10 p.m. to 6 a.m.
▪ Westbound SR-134 Northbound and Southbound San Fernando Road On Ramp TIME: 9 p.m. to 6 a.m.
About the Project
This project is building a high occupancy vehicle (HOV) lane in each direction along the Golden State Freeway (I-5) between the Ventura Freeway (SR-134) and Magnolia Boulevard in Burbank, a total distance of 5.4 miles (2.7 miles in each direction). It is also constructing sound walls and retaining walls.