From September 19, 2015 through October 2015, crews will be driving concrete piles to construct a new railroad bridge over Buena Vista Street.

MT
During work hours, Buena Vista Street northbound and southbound will be closed as follows:
  • Friday, September 18,at 10 p.m. to MondaySeptember 21, at 6 a.m.: Northbound and southbound Buena Vista Street from Winona Avenue to San Fernando Boulevard will be fully closed.
  • September 19 – October 4, 2015:  Northbound and southbound Buena Vista Street from Winona Avenue to San Fernando Boulevard will be fully closed on weekends from Saturday mornings at 6 a.m. to Sunday evenings at 8 p.m.
  • September 21 – October 16, 2015:  One lane of northbound Buena Vista Street from San Fernando Boulevard to Winona Avenue will be closed on weekdays, Monday through Friday, from 7 a.m. to 3 p.m. Flaggers will direct motorists.
For more information click here.

Work will occur during daytime hours unless otherwise noted.

CONSTRUCTION ACTIVITIES

SR 134 to Magnolia Boulevard

Bridge Widening Activities: Construction of concrete barrier rails at Western Avenue and Alameda Avenue and construction of bridge supports underneath Los Angeles River Bridge

Magnolia Boulevard to Buena Vista Street

BurCal Apartments8715

Burbank Western Channel: Forming and pouring abutment wall.

Old San Fernando Tunnel: Removal of barrier beams.

Empire Bridge: Installation of falsework to support freeway bridge structure.

Victory Place Bridge: Installation of lagging and excavation for bridge abutment.

Railroad Retaining Wall: Pile driving for the railroad retaining wall between Buena Vista Street and Hollywood Way (night work).

Burbank Boulevard at Southbound I-5 Off-ramp: Concrete crushing.

Future New Empire Avenue: Excavation work next to Sharky’s.

Southbound I-5 Retaining Walls: Construction of new retaining walls southbound I-5 between Empire Avenue and Burbank Boulevard.

Utility Work: Underground utility work on Empire Avenue between Valpreda Street and Keystone Street.

Closures and Detours

SR-134 to Magnolia Boulevard

The south side walkway/bike path along the Los Angeles River will be closed Monday, September 21, through Friday, September 25, at night from 10 p.m. to 6 a.m. For more information click here.
There will be intermittent closures of the Alameda Avenue and Western Avenue on-ramps Monday, September 21, through Friday, September 25, between 7 a.m. and 3:30 p.m.
Magnolia Boulevard to Buena Vista Street
Buena Vista Street northbound and southbound will be closed as follows:
+ Friday, September 18, at 10 p.m. to MondaySeptember 21, at 6 a.m.: Northbound and southbound Buena Vista Street from Winona Avenue to San Fernando Boulevard will be fully closed.
September 19 – October 4, 2015:  Northbound and southbound Buena Vista Street from Winona Avenue to San Fernando Boulevard will be fully closed on weekends from Saturday mornings at 6 a.m. to Sunday evenings at 8 p.m.
September 21 – October 16, 2015: One lane of northbound Buena Vista Street from San Fernando Boulevard to Winona Avenue will be closed on weekdays, Monday through Friday, from 7 a.m. to 3 p.m. Flaggers will direct motorists.

For more information click here.