Upcoming Closures for I-5 Freeway During Construction

0
483

The California Department of Transportation (Caltrans) will close the following lanes and ramps of the Golden State Freeway (I-5) as part of a $121 million improvement project to construct High Occupancy Vehicle (HOV or carpool) lanes in each direction along I-5 between SR-170 to Buena Vista Street. Closures are subject to change. Detours will be signed.

Golden State Freeway (I-5) Closures
Sunday January 13 through Saturday January 19, 2013

▪   Southbound I-5 Roscoe Boulevard Eastbound and Westbound On-RampTIME:  7 p.m. to 6 a.m. (until 10 a.m. on Saturday January 19th)▪   Northbound I-5 Roscoe Boulevard Eastbound and Westbound Off-RampTIME:  7 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 19th)
            9 a.m. to 3 p.m.▪   Northbound I-5 Sunland Boulevard Eastbound and Westbound Off-Ramp    TIME: 8 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)
   9 a.m. to 2 p.m.                         
▪   Northbound I-5 Sunland Boulevard Eastbound and Westbound On-Ramp     TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)
 ▪   Northbound I-5 Penrose Street Eastbound and Westbound Off-Ramp    TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)
             9 a.m. to 3 p.m.▪   Southbound I-5 Sunland Boulevard Eastbound and Westbound Off Ramp    TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th) ▪   Southbound I-5 Sunland Boulevard Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 19th)
           ▪   Northbound I-5 Tuxford Street Eastbound and Westbound Off and On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)   9 a.m. to 3 p.m.
▪   Northbound I-5 Lankershim Boulevard Eastbound and Westbound On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)   9 a.m. to 3 p.m.
▪   Northbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
    Off and On Ramps      TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)              9 a.m. to 3 p.m.

▪   Southbound I-5 Penrose Street Eastbound and Westbound Off-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)    9 a.m. to 3 p.m.
▪   Southbound I-5 Penrose Street Northbound and Southbound On-RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)   9 a.m. to 3 p.m.
▪   Southbound I-5 Lankershim Boulevard Eastbound and Westbound Off Ramp    TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)
▪   Southbound I-5 Lankershim Boulevard Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)   9 a.m. to 3 p.m.
    ▪   Southbound I-5 Brandford Street Eastbound and Westbound On RampTIME: 8 p.m. to 6 a.m. (Until 8 a.m. on Saturday January 19th)
▪   Southbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
    Off and On Ramps  TIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 19th)   9 a.m. to 3 p.m.
 ▪   Northbound I-5 Sheldon Street/Laurel Canyon Boulevard Eastbound and Westbound
    Off and On Ramps  TIME: 7 p.m. to 6 a.m.
   9 a.m. to 3 p.m.    
▪   Northbound I-5 Hollywood Way Eastbound and Westbound On and Off RampTIME: 8 p.m. to 6 a.m. (Until 12 p.m. on January 19th)
▪   Northbound I-5 Buena Vista Street Eastbound and Westbound On RampTIME: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 19th)▪   Southbound I-5 Hollywood Way Eastbound and Westbound Off and On RampsTIME: 8 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 19th)
▪   Northbound I-5 from Buena Vista Street to Sheldon Street/Laurel Canyon BoulevardTIME: One Lane: 8 p.m. to 6 a.m.    Three Lanes: 12 a.m. to 4 a.m. ▪   Southbound I-5 from Sheldon Street/Laurel Canyon Boulevard to Buena Vista Street     TIME: Up to Two lanes: 8 p.m.  To 6 a.m.    Three lanes: 12 a.m. to 6 a.m.
                               About the Project

Caltrans is building an HOV lane in each direction of I-5 between SR-170 and north of Buena Vista Street in Burbank.

 

The California Department of Transportation (Caltrans) will close the following lanes, ramps, and connectors of the Golden State Freeway (I-5) and the Ventura Freeway (SR-134) as part of a $57.8 million improvement project to construct High Occupancy Vehicle (HOV or carpool) lanes in each direction along I-5 between SR-134 and Magnolia Boulevard. Closures are subject to change. Detours will be signed.

Golden State Freeway (I-5) Closures
Tuesday January 8 through Monday January 14, 2013

*SB I-5 Eastbound and Westbound Alameda Avenue Off-ramp will have a long-term closure that will last approximately 60 days. It is expected to open on the week ending, January 12, 2013.

*Northbound I-5 Eastbound and Westbound Alameda Avenue Off-ramp will have a long-term closure that will last approximately 60 days. It is expected to open on the week ending, February 15, 2013.

▪   Southbound I-5 Eastbound and Westbound Alameda Avenue Off Ramp Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
▪   Southbound I-5 Eastbound and Westbound Alameda Avenue On Ramp Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
  9 a.m. to 3 p.m.
▪   Northbound I-5 Eastbound and Westbound Alameda Avenue Off Ramp Time: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 12th and 10 a.m. on Sunday January 13th)   9 a.m. to 3 p.m.
▪   Northbound I-5 Eastbound and Westbound Alameda Avenue On Ramp Time: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and   Sunday January 13th)   9 a.m. to 3 p.m.

▪   Southbound I-5 Western Avenue Westbound and Eastbound Off-Ramps TIME 7 p.m. to 6 a.m. (Until 10 a.m. Saturday January 12th and 12 p.m. on Sunday January 13th)
          9 a.m. to 3 p.m. ▪   Southbound I-5 Western Avenue Westbound and Eastbound On Ramps TIME 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
          9 a.m. to 3 p.m. ▪   Northbound I-5 Westbound Colorado Boulevard On Ramp Time: 10 p.m. to 6 a.m. (Until 7 a.m. on Saturday January 12th and 9 a.m. on Sunday January 13th)▪   Southbound I-5 Connector to Eastbound SR-134 TIME: 11 p.m. to 6 a.m. (Until 7 a.m. on Saturday January 12th)▪   Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue On-RampsTIME: 9 p.m. to 6 a.m. (Until 10 a.m. on Saturday January 12th and 11 a.m. on Sunday January 13th)
          ▪   Southbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue Off RampsTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
  9 a.m. to 3 p.m.▪   Northbound I-5 from SR-134 to Burbank BoulevardTIME: Up to two lanes – 10 p.m. to 6 a.m.
   Four lanes: 1 a.m. to 4 a.m.
▪ Northbound I-5 from Colorado Boulevard to SR-134TIME: Up to three lanes – 10 p.m. to 6 a.m.
   Four lanes: 1 a.m. to 4 a.m.
▪ Northbound I-5 Connector to Westbound SR-134 TIME: 12 a.m. to 6 a.m.
▪   Northbound I-5 Western Avenue Eastbound and Westbound On RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
           9 a.m. to 3 p.m. ▪   Northbound I-5 Western Avenue Eastbound and Westbound Off RampTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)
           9 a.m. to 3 p.m.

▪   Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue Off-RampsTIME: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 12th and 10 a.m. on Sunday January 13th)
   9 a.m. to 3 p.m.▪   Westbound SR-134 Connector to Northbound I-5 TIME: 11 p.m. to 6 a.m. (Until 9 a.m. on Sunday January 13th)
▪   Northbound I-5 Eastbound and Westbound Olive Avenue/Verdugo Avenue On-RampsTIME: 7 p.m. to 6 a.m. (Until 12 p.m. on Saturday January 12th and Sunday January 13th)  
▪   Southbound I-5 Westbound and Eastbound Burbank Boulevard On RampTime: 9 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 12th and 10 a.m. on Sunday January 13th)
▪   Westbound SR-134 at I-5 intersectionTime: Up to three lanes 8 p.m. to 6 a.m. (Until 9 a.m. on Saturday January 12th)    ▪   Southbound I-5 from Western Avenue to SR-134TIME: Up to two lanes: 1 a.m. to 4 a.m. (Until 6 a.m. on Sunday January 13th)▪   Southbound I-5 from Burbank Boulevard to SR-134TIME: Up to two lanes – 10 p.m. to 6 a.m.      
▪   Westbound SR-134 Northbound and Southbound San Fernando Road On Ramp TIME: 9 p.m. to 6 a.m. (Until 8 a.m. on Saturday January 12th and 9 a.m. on Sunday January 13th)    

About the Project

This project is building a high occupancy vehicle (HOV) lane in each direction along the Golden State Freeway (I-5) between the Ventura Freeway (SR-134) and Magnolia Boulevard in Burbank, a total distance of 5.4 miles (2.7 miles in each direction). It is also constructing sound walls and retaining walls.

    BurCal Apartments8715